Hawkins ISD
Board of
Trustees
General
contractor
selected;
Four of Nine
Upgrades
OK’d
By JOHN
SPARKS
Meeting in
regular
session
Tuesday,
December 19
the Hawkins
Independent
School
District
Board of
Trustees
selected the
bid of
general
contractor,
WRL
Contractors
to carry out
the
construction
and
renovation
project for
the
district’s
three
campuses.
The winning
bid was
14,333,000,
which was
$6,000 lower
than a
second bid
submitted by
RLM
Contractors.
Trustees
also added
four of nine
alternative
elements, at
an added
cost of
$141,500,
bringing the
total cost
up to
$14,474,500.
As predicted
by Brice
Davis, a
principal in
Thacker
Davis
Architects,
Inc.,
“aggressive
bidding” by
contractors1
brought the
primary
elements of
the project
in under the
$15-million
in bond
monies
approved by
HISD voters
just over a
year ago.
The winning
bidder is
expected to
begin the
initial
phases of
the
construction
work the
first week
of January.
Most
renovation
work will be
done after
students are
dismissed in
May 2007 and
before they
return in
August 2007.
The bids
were
submitted on
specifications
that
included
nine
alternatives
(all
upgrades
from the
original
specs) which
trustees
weighed
against the
$15-million
budget. At
the original
bid-letting,
1rustees
also
selected to
incorporate
four of
these
alternatives
into the
work plan.
These are:
a.)
a concrete
sidewalk and
gutter on
the
gymnasium
along the
Hawk Drive
side
(Alternative
#3);
b.)
a canopy
system with
sun
screening
from the
building
over the bus
loading/unloading
area and at
the stadium
entrance
(Alternative
#4);
c.)
arm chair
seating in
gymnasium,
instead of
bench
(Alternative
#6), and
d.)
upgrade to
higher grade
of carpeting
(Alternative
# 9).
Five other
alternatives
were not
added by the
trustees at
this time.
These
included:
paving of
stadium
parking lot,
paving of
student
parking lot,
interior
tile
wainscoting
on non-face
brick walls,
and
replacement
of the roof
on the
fifth-grade
pod of the
elementary
school.
On this
latter item,
the
administration
will
investigate
if there is
any relief
provided in
the warranty
on the
3-4year-old
roof which
is showing
signs of
blistering.
Rose also
reported
enrollment
data for the
district as
of November
30. The
district had
a total of
752 students
enrolled at
the end of
November, up
from 721 at
the same
date last
year.
Comparative
figures for
each campus
are: high
school 205
from 198;
middle
school 152
from 148 and
elementary
school 395
from 366.
Trustees are
next
scheduled to
meet January
22 to review
the
Superintendent’s
evaluation.
A special
meeting of
the board
can be
called with
72-hours
notice.